REPLACE FISHER HOUSE PARKING

Client: Department of Veterans Affairs

Location: Seattle, WA

Contract Value: $811,399

Completed: March 2008

Project consisted of removing two undeveloped and forested areas that were adjacent to the medical center and replacement with surface parking lots. The project was fast-track with needed parking stalls delivered three months ahead of the desired contract completion date. As Prime Contractor, NCS self-performed the mass excavation, site demolition, rough grading, utility relocations, utility upgrades, storm drainage systems, fine grading and signage.